Analysis of Internal and External Factors on Project Performance Based on Risk Management in Smelter Construction

Authors

  • Priyo Adi Pamungkas INDONESIA
  • Budi Susetyo INDONESIA

DOI:

https://doi.org/10.32832/astonjadro.v13i2.15378

Keywords:

internal factors; external factors; project performance; risk management; smelter.

Abstract

The mining industry has projects that require effective risk management, especially in terms of smelter construction. Smelter construction is a complex process and requires attention to various internal and external factors that can affect project performance. This research uses quantitative research methods. In this study, the data collection method that will be used is a questionnaire technique. The data that has been collected is then analyzed using statistical analysis techniques using Structural Equation Modeling - Partial Least Square (SEM PLS). The results showed that the risk factors that obtained the most dominant value with a high risk category consisted of 8 indicators of internal and external risk factors, namely labor shortages, rising material prices, inexperienced project managers and experts, supplier changes close to project closure causing cost overuns, unclear project priorities where less important work is completed, uncertain weather, contaminated environment pollution, weather during construction activities. Internal and external factors together have a significant effect on project performance in terms of cost, quality and time in direct effect.

Author Biographies

Priyo Adi Pamungkas, INDONESIA

Master of Civil Engineering Study Program, Faculty of Engineering, Universitas Mercu Buana Jakarta

Budi Susetyo, INDONESIA

Master of Civil Engineering Study Program, Faculty of Engineering, Universitas Mercu Buana Jakarta

References

Agung, M., Ariananto, E., & Adi, W. (2022). Peningkatan Investasi Dan Hilirisasi Nikel Di Indonesia. 6(2), 4009–4020.

Hair, J. F., Hult, G. T. M., Ringle, C. M., & Sarstedt, M. (2017). A primer on partial least squares structural equation modeling (PLS-SEM)(Sage Publications Inc, Thousand Oaks, CA).

Kementerian ESDM. (2020). Peluang Investasi Nikel Indonesia. In Kementerian Energi dan Sumber Daya Mineral Republik Indonesia (pp. 5–10).

Nurdiana, A., & Setiabudi, B. (2018). Aplikasi Manajemen Risiko Pada Proyek Jalan Tol Semarang-Solo Ruas Bawen-Solo| Nurdiana | Jurnal Proyek Teknik Sipil. Jurnal Proyek Teknik Sipil, 1(1), 21–28.

Pemerintah RI. (2009). Undang Undang Pertambangan Mineral Dan Batubara. Uu No 4 Tahun 2009 Tentang Pertambangan Dan Batubara, 4.

Ridwan, W. A. (2021). Manajemen risiko di perguruan tinggi. 05(September), 8402–8411.

Sudaryono, Dr. 2017. Metodologi Penelitian. Depok:PT.Raja Grafindo.

Sugiharto, R. (2020). Analisis Faktor-Faktor Dominanmanajemen Risiko Terhadap Kinerja Keuangan Proyek Tahap Konstruksi. Jurnal TESLINK : Teknik Sipil Dan Lingkungan, 2(2), 1–11. https://doi.org/10.52005/teslink.v2i2.41

Susanti, R. (2022). Identifikasi dan Penanganan Risiko K3 pada Proyek. Poli-Teknologi, 10(1), 55–68.

v. M. buyanov. (1967). Bab III (SEM-PLS). Angewandte Chemie International Edition, 6(11), 951–952., 21–37.

Wijaya, E. K., Setyowati, E. W., & Zaika, Y. (2017). Analisis Pengendalian Risiko Terhadap Peningkatan Kinerja Pekerjaan Konstruksi (Studi Kasus Asrama Haji Gorontalo). Rekayasa Sipil, 11(2), 149–158. https://doi.org/10.21776/ub.rekayasasipil/2017.011.02.9

Arjon, A., & Hardjomuljadi, S. (2024). Potential Disputes in Government Bank Building Construction Projects in Indonesia. ASTONJADRO, 13(1), 48–66. https://doi.org/10.32832/astonjadro.v13i1.14347

Nuranto, A. (2024). Potential Supervision Consultant Contract Disputes Due to Extension of Contractor Time in DKI Jakarta Regional Government Project Based on Fidic White Book. ASTONJADRO, 13(1), 283–294. https://doi.org/10.32832/astonjadro.v13i1.14772

Salsabila, A., Setyowulan, D., & Arifi, E. (2024). Analysis Value Engineering at Work Apartment Building Wall. ASTONJADRO, 13(1), 245–250. https://doi.org/10.32832/astonjadro.v13i1.14713

Irvania, A., Pujiraharjo, A., & Suharyanto, A. (2024). Resource Leveling Optimization Using Different Objective Functions on Building Project. ASTONJADRO, 13(1), 182–191. Retrieved from https://ejournal.uika-bogor.ac.id/index.php/ASTONJADRO/article/view/14563

Sabariah, I., Syaiful, S., & Ida Hayati, N. (2012). ANALISIS METODE NETWORK PLANNING DAN S-CURVE PROYEK KONSTRUKSI DI BOGOR. ASTONJADRO, 1(1), 28–34. https://doi.org/10.32832/astonjadro.v1i1.782

Published

2024-05-22

How to Cite

Adi Pamungkas, P., & Susetyo, B. (2024). Analysis of Internal and External Factors on Project Performance Based on Risk Management in Smelter Construction. ASTONJADRO, 13(2), 537–549. https://doi.org/10.32832/astonjadro.v13i2.15378

Issue

Section

Articles