Analysis of the Influence of Order Variation Factors on the Costs and Time of Implementing Channel Diversion Infrastructure Construction Projects in Residential Areas

Authors

  • Ghazi Ghossan Hindami INDONESIA
  • Agus Suroso INDONESIA
  • Mawardi Amin INDONESIA

DOI:

https://doi.org/10.32832/astonjadro.v13i3.16249

Keywords:

variation order; time performance; cost performance; infrastructure; housing area.

Abstract

Tangerang is one of the big cities that is developing in Indonesia. Along with the development of the city, one sector that is increasingly developing is the housing sector. In implementing construction projects, problems are often faced, one of which is the occurrence of changes. Almost all existing projects experience variation orders (VO). Variation orders always have cost and time implications. Whatever the variation, there will be risks to the work being done, both in terms of work delays and additional costs that must be borne.  Research using the SEM PLS method was carried out to find out what factors cause variation orders and how they affect time and cost performance in channel diversion infrastructure projects in residential areas. Based on the results of responses from correspondents, the significant value that influences project performance is planning and design with indicators of errors in planning drawings. Based on the results of the cost performance analysis for the amount of costs resulting from variation orders on work, the total increase was IDR. 10.516.305.346 and for less work the total is IDR. 6.628.461.533 around 12.96% of the initial contract price and the results of the time performance analysis for the amount of time resulting from variation orders on the project work show that there was a time extension of 5 months or 125%.

Author Biographies

Ghazi Ghossan Hindami, INDONESIA

Master Civil Engineering, Mercubuana University, Jakarta

Agus Suroso, INDONESIA

Doctor Civil Engineering, Mercubuana University, Jakarta

Mawardi Amin, INDONESIA

Doctor Civil Engineering, Mercubuana University, Jakarta

References

Abdillah & Jogiyanto. 2011. Partial Least Square (PLS), Alternatif Structural Equation Modeling (SEM) dalam Penelitian Bisnis (Buku). Andi Yogyakarta.

Albtoosh. Ja’far A & Ahmad tarmazi H (2017) Variation Orders Causes In Construction Buildings Projects In Jordan. Global Journal of Engineering Science and Research Management [Albtoosh* 4(9): September, 2017] ISSN 2349-4506.

Alhadithi, W., I. Naji, H., & N. Zehawi, R. (2021). Identifying the key causes and impacts of variation orders in Iraqi Construction Projects. Diyala Journal of Engineering Sciences, 14(2), 18–27. https://doi.org/10.24237/djes.2021.14202.

Alfian Malik, (2010). Pengantar Bisnis Jasa Pelaksana Konstruksi. Yogyakarta: Cv Andi Offset.

Alzara, M. (2022). Exploring the impacts of change orders on performance of construction projects in Saudi Arabia. Advances in Civil Engineering, 2022, 1–11.

Antuwan, Sintayehu T (2016) Assessment on the Impact of Variation Order on Project Performance in the Case of 40/60 Housing Project in Addis Ababa. Addis Ababa Science & Techology University School Of Civil Engineering & Construction.

Arain, F. M., & Pheng, L. S. (2006). Developers' views of potential causes of variation orders for institutional buildings in Singapore. Architectural Science Review, 49(1), 59–74. https://doi.org/10.3763/asre.2006.4908

Badan Standardisasi Nasional. 2004. SNI 03-1733-2004. Tata cara perencanaan lingkungan perumahan di perkotaan Frick, Heinz. 1984. Rumah Sederhana. Yogyakarta: Penerbit Kanisius.

Barrie, Donald S, and Paulson, Boyd C Jr.(1992). Professional construction management, third edition. Singapore:Mc Graw-Hill.

Chen, Chao. (2015) A Proactive Approach for Change Management and Control on onstruction Project. Doctor of Philosophy in Engineering – Civil and Environmental Engineering University of California, Berkeley.

Natasasmita, G., Murtejo, T., Chayati, N., & Lutfi, M. (2020). STUDI KELAYAKAN INVESTASI FINANSIAL (Studi Kasus: Perumahan BIA Residence). ASTONJADRO, 7(1), 1–7. https://doi.org/10.32832/astonjadro.v7i1.2272

Anwar, S., & Ida Hayati, N. (2013). ANALISIS PEMAKAIAN METODE EARNED VALUE SEBAGAI ALAT PENGENDALIAN PROYEK. ASTONJADRO, 2(2), 19–28. https://doi.org/10.32832/astonjadro.v2i2.795

Sabariah, I., Syaiful, S., & Ida Hayati, N. (2012). ANALISIS METODE NETWORK PLANNING DAN S-CURVE PROYEK KONSTRUKSI DI BOGOR. ASTONJADRO, 1(1), 28–34. https://doi.org/10.32832/astonjadro.v1i1.782

Khatimi, H., Fardian, M. R., & Sari, Y. (2021). EFFECTIVENESS OF APPLYING BIM BASED COST ESTIMATION IN DEVELOPMENT OF THE SYAMSUDIN NOOR AIRPORT PROJECT BANJARMASIN. ASTONJADRO, 10(1), 109–116. https://doi.org/10.32832/astonjadro.v10i1.4200

Marguna, A., Ida Hayati, N., & Rulhendri, R. (2012). APLIKASI TEKNIK EARNED VALUE DALAM PENGENDALIAN BIAYA DAN WAKTU PROYEK (Studi Kasus Proyek Pembangunan Gedung SDN Beji 2 Depok). ASTONJADRO, 1(2), 44–56. https://doi.org/10.32832/astonjadro.v1i2.789

Syaiful Syaiful, Soni Sutarsa, (2020). Analysis of Sustainable Financial Investment Feasibility Study on Housing Casase Cetrene. Proceeding of the 5th North American IEOM Society International Conference, Detroit, Michigan, USA. (5). 3631-3639. https://www.ieomsociety.org/detroit2020/papers/716.pdf

Dharmawati Pratama S, Hadi, P., Hamkah, H., Mansyur, M., Haerul P., Arman, H., Andi Arifuddin I., Andi I., Syaiful, S., (2024). MANAJEMEN PROYEK INFRASTRUKTUR. CV. Tohar Media. Makassar.

Published

2024-09-22

How to Cite

Hindami, G. G., Suroso, A., & Amin, M. (2024). Analysis of the Influence of Order Variation Factors on the Costs and Time of Implementing Channel Diversion Infrastructure Construction Projects in Residential Areas. ASTONJADRO, 13(3), 941–957. https://doi.org/10.32832/astonjadro.v13i3.16249

Issue

Section

Articles