Analysis the Influence of Manpower, Material, Machine, Method, Money and Environment on the Time Performance of Implementing Cold Storage Building Projects
DOI:
https://doi.org/10.32832/astonjadro.v14i1.16389Keywords:
time performance; cold storage building; multiple linear regression analysis; SPSS.Abstract
Cold Storage Building is a building specifically designed to maintain room temperature in very cold conditions which functions as a commodity preservation area so that it can be stored fresh for a long period of time. When constructing a Cold Storage Building, a very specialist construction process is required. Therefore, it must be carried out using a certain construction method (modular construction), using special Materials (sandwich panels), requiring several specialist subcons & a lack of experienced workers. These conditions make the challenge of building a Cold Storage Building more difficult, which can affect the time performance of the project. This research aims to analyze factors that can influence time performance in the implementation of the Cold Storage Building construction project using the Multiple Linear Regression Analysis method. Based on data analysis, the equation Y = 3.166 + 0.108 X1 + 0.208 X2 + 0.040 X3 + 0.112 X4 + 0.164 Based on the results of the Coefficient of Determination Test, simultaneously Manpower Factors (X1), Material Factors (X2), Machine Factors (X3), Method Factors (X4), Money Factors (X5) and Environment Factors (X6) have an influence contribution of 87.6 % of Time Performance (Y). Meanwhile, for the results of the most dominant factors analysis using Beta Standardized x Zero-Order, it was found that the Material Factors (X2) was the most dominant factors that could influence time performance with an influence value of 34.01%. Considerations in determining alternative solutions to improve time performance on Cold Storage Building construction projects are carried out on the most dominant factors, namely the Material Factors (X2).
References
Ade & Santoso, 2022. Delay Factors Analysis and Dynamic System Modeling on the Liquid Petreleum Gas Tank EPC Project in Kupang. Journal Research of Social Science Economics, & Management.
Alam & Putra, 2023. Kajian Faktor-Faktor yang Mempengaruhi Keterlambatan pada Proyek Konstruksi Gedung Bertingkat. Journal of Civil Engineering and Vocational Education, Vol 10 No.2 Juni, 2023.
Apriliyani & Amin, 2019. Analisis Keterlambatan Berbasis Manajemen Risiko Pada Proyek Warehouse Lazada Tahap 2. Rekayasa Sipil, Vol. 8 No. 2. Sept.
Asmi & Djamaris, 2021. Project Delay Factors Ranking among Contractor, Client and Project Management Consultant in Construction Industry. Widyakala Journal, Vol 8, Issue 2, September 2021.
Aulia & Husin, 2022. Dynamic Model-Based Risk Manageability in the Modular Construction of High-Rise Residential Buildings to Improve Project time Performance. Civil Engineering and Architecture 10(6): 2541-2553, DOI: 10.13189/cea.2022.100623.
Azwar. 1997. Metode Penelitian Jilid I, Yogyakarta: pustaka pelajar.
Din, Raza & Khan, 2020. Comparative Analysis Of Factors Causing Delay In Residential Construction Projects In Pakistan. American Society of Civil Engineers.
Ghozali, Imam. 2018. Aplikasi Analisis Multivariate dengan Program IBM SPSS 25. Badan Penerbit Universitas Diponegoro: Semarang.
Gusbian & Amin, 2023. Analisis Risiko Biaya Pekerjaan Peningkatan Jalan di Kabupaten Serang. Syntax Literate: Jurnal Ilmiah Indonesia.
Haryo, Mulyadi & Iskandar, 2020. Delay Factors in Building Construction Project of State Elementary School. Civil Engineering Journal.
Henong, S. B, 2022. Dampak Pandemi Covid - 19 terhadap Penyelesaian Proyek Konstruksi: Tinjauan Literatur Sistematis. Journal of Sustainable Construction.
Hwang, Zhao & Low, 2013. Critical success factors for enterprise risk management in Chinese construction companies. Constr. Manag. Econ., vol. 31, no. 12, pp. 1199– 1214, 2013, DOI: 10.1080/01446193.2013.867521.
Ismail Cengiz Yilmaz & Deniz Yilmaz. 2020. Optimal capacity for sustainable refrigerated storage buildings. Case Studies in Thermal Engineering. Published by Elsevier Ltd.
Khatib, Poh & El-Shafie, 2018. Delay Factors in Reconstruction Projects: A Case Study of Mataf Expansion Project. Sustainability, Published by MDPI.
Kurniawan, Saputra & Saputro, 2020. Development of Delay Factors Model for Substructure Works in Building Construction. Advances in Engineering Research, volume 203.
Latif, Al Saadi & Rahman, 2019. Identification of Delay Factors in Oman Construction Industry. International Journal of Sustainable Construction Engineering and Technology Vol. 10 No. 1 (2019) 34-45.
Mamesah, Walangitan & Arsjad, 2023. Analisis Faktor – Faktor Penyebab Keterlambatan Proyek Konstruksi Pada Pembangunan Christian Center Tahap II, Jurnal TEKNO, Volume 21, No. 83.
Moh Nazir, 2005. Metode Penelitian. Ghalia Indonesia, Jakarta.
Putra, Fatmawati & Mas’idah, 2020. Analisa Waktu & Biaya Pembangunan Gedung Gudang Dan Kantor PT ABC Semarang Dengan Earned Value Analysis. Konferensi Ilmiah Mahasiswa Unissula, ISSN. 2720-9180
Putra, Sari & Situmorang, 2023. Factors Analysis of Construction Projects Delay in Balikpapan City, Jurnal Teknik Sipil: Rancang Bangun, Vol. 09 No. 01 April (2023) Halaman Artikel (017-024).
Rahmawati, Nia, & Tenriajeng, Andi Tenrisukki. (2020). Analisis Manajemen Risiko Pelaksanaan Pembangunan Jalan Tol (Studi Kasus : Proyek Pembangunan Jalan Tol Bekasi-Cawang-Kampung Melayu). Rekayasa Sipil, 14(1), 18–25. https://doi.org/10.21776/ub.rekayasasipil.2020.014.01.3.
Shui, Rifai & Pamadi, 2023. The Analysis Performance of Project Delays in Pile Foundation Work: A Case Study Batam Island. International Journal of Entrepreneurship and Business Development.
Singarimbun, Effendi. 1995. Metode Penelitian Survey. LP3ES: Jakarta.
Song & Wei, 2022. Quality Risk Management Algorithm for Cold Storage Construction Based on Bayesian Networks. Computational Intelligence and Neuroscience.
Sudjana. 2005. Metode Statistika Edisi ke 6. Bandung: Tarsito.
Sugiyono. 2017. Metode Penelitian Kuantitatif, Kualitatif, dan R & D. Bandung: Alfabeta, CV.
Sutisna, Iskandar & Suliantoro, 2021. Critical Risks Factors (CRF) for Construction Delay Mitigation in Provincially/ Municipally-Owned Corporation (BUMD). Proceedings of the First Multidiscipline International Conference.
Triarman & Sekarsari, 2018. Analisis Faktor Penyebab Keterlambatan Waktu Pada Pekerjaan Struktur Atas Proyek Konstruksi. Jurnal Penelitian dan Karya Ilmiah Lembaga Penelitian Universitas Trisakti.
Viles, Rudeli & Santilli, 2020. Causes of delay in construction projects: a quantitative analysis. Engineering. Construction and Architectural Management, Emerald Publishing.
Yap, Goay, Woon & Skitmore, 2020. Revisiting critical delay factors for construction: Analysing projects in Malaysia. Alexandria Engineering Journal, published by Elsevier B.V.
Zidane & Andersen, 2018. The top 10 universal delay factors in construction projects. International Journal of Managing Projects in Business, Emerald Publishing.
Downloads
Published
How to Cite
Issue
Section
License
Copyright (c) 2025 ASTONJADRO
This work is licensed under a Creative Commons Attribution-ShareAlike 4.0 International License.
Paper submitted to ASTONJADRO is the sole property of the Astonjadro Journal. Unless the author withdraws the paper because he does not want to be published in this journal. The publication rights are in the journal Astonjadro.ASTONJADRO
LICENSE
This work is licensed under a Creative Commons Attribution-ShareAlike 4.0 International License.
Based on a work at http://ejournal.uika-bogor.ac.id/index.php/ASTONJADRO