Implementation of Time Performance Control, Donator System, and Coordination Level in Mosque Construction in Indonesia
DOI:
https://doi.org/10.32832/astonjadro.v14i2.17559Keywords:
design; donors; coordination; change orders; availability of human resource skills; time performance.Abstract
The process of building a mosque requires competent human resources and community participation. In addition, the availability of funds and support from the government or local authorities can also affect the duration of mosque construction. This study aims to analyze the effect of change orders on the availability of human resource skills and project implementation time performance in West Nusa Tenggara. The research method with quantitative surveys to determine the relationship between change orders, availability of HR skills and time performance will be made in a path diagram model, and analyzed using SEM-PLS with a sample of 104 respondents. The results of the study indicate that design, donors, and coordination together have a significant influence on change orders in mosque construction projects. Change orders in mosque construction projects have a significant impact on human resources, Human resource competence has a significant influence on the time performance of mosque construction projects and Controlling design, donor, and coordination variables is the key to reducing the frequency of order changes, increasing human resource competence, and ensuring optimal time performance in mosque construction projects.
References
Awad, J. (2021). The current trends in mosque architecture in the northern cities of the United Arab Emirates (UAE). Archnet-IJAR: International Journal of Architectural Research, 15(3), 854–871.
Belferik, R., Andiyan, A., Zulkarnain, I., Munizu, M., Samosir, J. M., Afriyadi, H., … Ichsan, M. (2023). Manajemen Proyek: Teori & Penerapannya. PT. Sonpedia Publishing Indonesia.
Brotodiharjo, S. (2005). Donasi Sumbangan Masyarakat. Yogyakarta: Andi Offset.
Demissew, A., & Abiy, F. (2023). Causes and Impacts of Delays in Ethiopian Public Construction Projects (Case on Debre Markos University Construction Projects). Advances in Civil Engineering, 2023. https://doi.org/10.1155/2023/6577676
Fahmi, R. A. (2022). Transformation of mosque management through Islamic social enterprise concept. Journal of Islamic Economics Lariba, 8(1), 157–178.
Falah, M. F., Quthny, A. Y. A., & Muzakki, A. (2023). Explication of Mosque Construction Funds from Roadside Charity Donations in the Perspective of Islamic Law Sociology. Hayula: Indonesian Journal of Multidisciplinary Islamic Studies, 7(2), 207–226.
Gurgun, A. P., & Koc, K. (2023). The role of contract incompleteness factors in project disputes: A hybrid fuzzy multi-criteria decision approach. Engineering, Construction and Architectural Management, 30(9), 3895–3926.
Hair, J. F., Risher, J. J., Sarstedt, M., & Ringle, C. M. (2019). When to use and how to report the results of PLS-SEM. European Business Review, 31(1), 2–24.
Handoko, T. H. (2016). Manajemen personalia dan sumberdaya manusia. Yogyakarta: Bpfe.
Hasibuan. (2019). Manajemen Sumber Daya Manusia. Jakarta: Bumi Aksara.
Husein, A. A., & Majdi, A. (2020). Assessment of risk management and evaluate the level of risk in construction project: Case Study, 2(1), 66–72. https://doi.org/10.47577/technium.v2i1.43
Kaçar, Y. (2020). DİYANET İŞLERİ BAŞKANLIĞI CAMİ YAPIMI VE BAKIMI FONU BÜTÇE VE MUHASEBE DÜZENİ. The Journal of Social Science, 4(8), 705–719.
Keane, P., Sertyesilisik, B., & Ross, A. D. (2010). Variations and change orders on construction projects. Journal of Legal Affairs and Dispute Resolution in Engineering and Construction, 2(2), 89–96. https://doi.org/10.1061/(ASCE)LA.1943-4170.0000016
Kuswandari, A. D., Koesmargoro, A., & Ervianto, W. I. (2018). Pengaruh Dampak Contract Change Order Terhadap Kinerja Kontraktor Proyek Studi Kasus: Rehabilitasi Jembatan Ngablak. Jurnal Teknik Sipil, 14(4), 255–282. https://doi.org/10.24002/jts.v14i4.2001
Lakaoni, K. D., & Waty, M. (2023). Dampak Change Order Proyek Konstruksi Bangunan Gedung Bertingkat Sedang. JMTS: Jurnal Mitra Teknik Sipil, 6(2), 367–382.
Lapidus, A., & Abramov, I. (2018). Systemic integrated method for assessing factors affecting construction timelines. In MATEC Web of Conferences (Vol. 193, p. 5033). EDP Sciences. https://doi.org/10.1051/matecconf/201819305033
Nawawi, H. (2015). Perencanaan Sumber Daya Manusia. Yogyakarta: Gajah Mada University Press.
Pratama, F. Y., Zacoeb, A., & Wijaya, M. N. (2023). Identification of Dam Construction Risks to Job Owners (Dam Construction in East Java). Journal of Mechanical, Civil and Industrial Engineering, 4(2), 25–33.
Purwanto, S., Alfandi, B., & Tiana, E. (2019). Analisa Produktivitas Tenaga Kerja Terhadap Biaya Dan Waktu Pelaksanaan Pada Pekerjaan Pembangunan Proyek Masjid Al-Istighfar Di Sindang Panon, Kab. Tangerang. Structure, 1(1), 7–17. https://doi.org/10.31000/civil.v1i1.6803
Putra, H. E., & Sulistio, H. (2020). Pengaruh Change Order Terhadap Biaya, Mutu, Dan Waktu Pada Proyek Konstruksi Gedung Bertingkat. JMTS: Jurnal Mitra Teknik Sipil, 1349–1362.
Rini, I. P. (2017). Pengaruh Produktivitas Tenaga Kerja Terhadap Kinerja Waktu Proyek Pada Bangunan Bertingkat. Jurnal Infrastruktur, 3(2), 127–135. https://doi.org/10.35814/infrastruktur.v3i2.715
Sherwood, J. (2023). Identifying and Managing Project Risk 3rd Edition Book Notes (3rd ed.). London: AMACOM.
Siagian, S. P. (2018). Manajemen Sumber Daya Manusia (26th ed.). Jakarta: Bumi Aksara.
Soeharto, I. (1999). Manajemen Proyek. Jakarta: Erlangga.
Subekhi, A., & Jauhar, M. (2012). Manajemen Sumber Daya Manusia (Insani). Jakarta: Prestasi Pustaka Raya.
Syah, I. M. (2004). Manajemen Proyek. Jakarta: Pustaka Utama.
Wirabakti, D. M., Abdullah, R., & Maddeppungeng, A. (2017). Studi Faktor-Faktor Penyebab Keterlambatan Proyek Konstruksi Bangunan Gedung. Konstruksia, 6(1). https://doi.org/10.24853/jk.6.1.%25p
Downloads
Published
How to Cite
Issue
Section
License
Copyright (c) 2025 ASTONJADRO

This work is licensed under a Creative Commons Attribution-ShareAlike 4.0 International License.
Paper submitted to ASTONJADRO is the sole property of the Astonjadro Journal. Unless the author withdraws the paper because he does not want to be published in this journal. The publication rights are in the journal Astonjadro.ASTONJADRO
LICENSE
This work is licensed under a Creative Commons Attribution-ShareAlike 4.0 International License.
Based on a work at http://ejournal.uika-bogor.ac.id/index.php/ASTONJADRO