Integrated Risk Analysis of Manager Competency in Bali Construction Delays
DOI:
https://doi.org/10.32832/astonjadro.v15i3.22322Keywords:
construction delays, project manager competency, recruitment system, risk identification, systematic literature review.Abstract
Construction project delays remain a critical challenge in Indonesia's construction industry, particularly in Bali's strategic tourism development areas. This qualitative study identifies and categorizes risk factors related to project manager (PM) quality and recruitment systems that contribute to construction project delays in Bali through systematic literature review and expert validation. Using rigorous content analysis methodology, this research analyzed 25 national and international peer-reviewed journal articles published between 2020-2025, complemented by PMBOK® Guide Seventh Edition standards, and validated findings through consultation with five senior construction practitioners in Bali. Through thematic content analysis and constant comparative method, the study identifies 16 Risk Events and 38 Risk Agents categorized into eight dimensions: PM competency, recruitment & HRM, planning & system, coordination & communication, resource management, vendor & supply chain, organizational culture, and external factors. Results reveal that PM competency-related factors constitute the most critical risk agents, with weak communication ability appearing in 76% of literature, weak planning ability in 72%, and insufficient leadership in 68%. Recruitment system deficiencies, including lack of competency-based selection criteria (24%), unstructured recruitment processes (20%), and inadequate training programs (32%), significantly contribute to PM performance gaps. The integration of these findings with Bali's unique construction context—including high-end tourism project specifications, international client expectations, complex cultural regulations, and seasonal workforce dynamics—provides comprehensive understanding of project delay root causes. This study offers the first systematic qualitative framework linking PM quality and recruitment systems to construction delays in Bali's tourism construction context, contributing theoretical understanding grounded in international literature and validated through local expert perspectives.
References
[1]. Ahmad, R., & Sari, D. (2024). Digital transformation and project management success in Indonesian construction industry. Journal of Construction Engineering and Management, 150(8), 04024089.
[2]. Ali, H., & Al-Sabahi, A. (2024). Critical role of project managers in large-scale construction project success. Journal of Construction Engineering and Management, 150(3), 04024012.
[3]. Darmawan, I. (2021). Stres kerja dan kinerja manajer proyek konstruksi. Jurnal Manajemen Konstruksi, 8(2), 45-58.
[4]. Domingo, R. (2024). Pengaruh pengalaman project manager dan mandor terhadap keberhasilan proyek dengan metode Last Planner System. Jurnal Teknik Sipil, 31(1), 23-36.
[5]. Dudek, M. (2021). The role of project managers in process approach and IPMA competencies. Procedia Computer Science, 192, 2401-2410.
[6]. Emiyani, V., & Rusmana, D. (2023). Kualitas manajer proyek di industri konstruksi Indonesia. Indonesian Journal of Construction Management, 4(2), 89-104.
[7]. Fernando, S. (2022). Kepemimpinan project manager dan kinerja supply chain dalam proyek konstruksi. Jurnal Manajemen Proyek, 15(3), 112-128.
[8]. Haider, S. (2024). Impact of emotional intelligence on megaproject success: Evidence from CPEC projects. International Journal of Project Management, 42(2), 156-172.
[9]. Indrawati, P., & Kumar, S. (2024). Cultural dimensions in Indonesian construction project management: A contemporary analysis. International Journal of Managing Projects in Business, 17(3), 445-462.
[10]. Kassem, M. (2023). Project manager effectiveness and construction delays: A systematic review. Engineering, Construction and Architectural Management, 30(4), 1523-1545.
[11]. Lincoln, Y. S., & Guba, E. G. (1985). Naturalistic inquiry. Sage Publications.
[12]. Maharani, S., Dewi, T., & Rahman, A. (2023). House of Risk application in construction project delay analysis. Engineering, Construction and Architectural Management, 30(8), 3245-3262.
[13]. Mairizal, A. (2020). Identifikasi faktor kompetensi project manager pada proyek EPC di Indonesia. Jurnal Teknik Industri, 12(2), 134-147.
[14]. Moradi, K. (2020). Competencies required for managing collaborative construction projects. International Journal of Construction Management, 22(8), 1567-1582.
[15]. Nakamura, T., & Singh, P. (2024). Integrated enterprise risk management in construction: COSO 2023 framework application. Risk Management, 26(2), 156-174.
[16]. Nguyen, H. (2021). Critical factors affecting labor productivity in construction projects: Case study in Vietnam. International Journal of Civil Engineering, 19(8), 983-998.
[17]. Nursanti, E. (2023). Gaya komunikasi project manager dalam meningkatkan performa proyek. Jurnal Komunikasi Bisnis, 10(1), 78-94.
[18]. Patel, N., & Johnson, R. (2024). PMI Talent Triangle 2.0: Digital fluency integration and project success correlation. Project Management Journal, 55(1), 23-38.
[19]. Paul, M. (2023). Performance index analysis of construction project managers in developing economies. Journal of Engineering, Design and Technology, 21(4), 1089-1106.
[20]. Pavate, S. (2024). Factors affecting time, cost, and quality in construction projects. International Journal of Research and Innovation in Social Science, 8(3), 234-251.
[21]. PMI. (2021). A Guide to the Project Management Body of Knowledge (PMBOK® Guide) – Seventh Edition. Project Management Institute.
[22]. Pradnyadari, I. A. (2021). Pengaruh komitmen manajer proyek terhadap kesuksesan proyek konstruksi di Bali. Jurnal Spektran, 9(2), 156-167.
[23]. Pratama, H. (2024). Pengaruh kebijakan project manager terhadap motivasi kerja karyawan konstruksi. Jurnal Manajemen dan Bisnis, 12(1), 45-62.
[24]. Pratama, H., & Hassan, M. (2023). Regulatory compliance strategies and project performance in Indonesian construction industry. Construction Law Journal, 39(4), 412-428.
[25]. Pujawan, I. N., & Geraldin, L. H. (2009). House of risk: A model for proactive supply chain risk management. Business Process Management Journal, 15(6), 953-967.
[26]. Rauzana, A. (2022). Pengaruh kompetensi manajer proyek terhadap kesuksesan proyek konstruksi di Indonesia. Teras Jurnal, 12(2), 234-248.
[27]. Razak, A., Ibrahim, M., & Yusof, N. (2023). Financial constraints and project scheduling disruptions in construction industry. International Journal of Research and Innovation in Social Science, 9(2), 156-171.
[28]. Rodriguez, A., & Chen, W. (2024). Environmental complexity and adaptive competency requirements in Southeast Asian construction projects. International Journal of Project Management, 42(3), 89-104.
[29]. Said, R., & Gabriel, J. (2021). Managerial competence and project delivery in post-pandemic construction. Engineering, Construction and Architectural Management, 28(5), 1450-1467.
[30]. Sari, L., & Wijaya, K. (2024). Digital maturity and construction project performance: Evidence from Indonesian construction companies. Journal of Information Technology in Construction, 29, 234-251.
[31]. Sarpin, N. (2021). Sustainability competencies for construction project managers in Malaysia. Smart and Sustainable Built Environment, 10(2), 178-195.
[32]. Sonelma, A. (2022). Analisis kompetensi project manager pada proyek pembangunan Apartemen X. Jurnal Dimensi Pratama Teknik Sipil, 11(1), 89-98.
[33]. Surya, I., & Dewi, R. (2024). Stakeholder engagement risks in Indonesian infrastructure projects. International Journal of Construction Management, 24(8), 1234-1248.
[34]. Tao Ha, N. (2018). Impact of leadership competencies on construction project success. Journal of Construction Engineering and Management, 144(4), 04018014.
[35]. Vianda, R. (2024). Kompetensi manajer proyek pada proyek konstruksi rel kereta api. Jurnal Transportasi dan Infrastruktur, 9(1), 45-61.
[36]. Widodo, A., Sari, P., & Rahman, B. (2024). Adaptive competency and project delay reduction in Indonesian construction industry. Asian Journal of Civil Engineering, 25(4), 1567-1582.
[37]. Widyarsana, I. (2023). Identifikasi variabel kompetensi project manager dalam proyek konstruksi Kabupaten Badung. Paduraksa, 12(2), 112-126.
[38]. Williams, T. (2022). Extended complexity framework for contemporary construction projects. International Journal of Project Management, 40(6), 567-581.
[39]. Winoto, S. (2022). Faktor penyebab dan dampak keterlambatan proyek konstruksi. Jurnal Rekayasa Sipil, 16(3), 178-192.
[40]. Yusuf, M. (2022). Profesionalisme manajer proyek dalam pelaksanaan proyek konstruksi. Jurnal Manajemen Teknologi, 21(2), 145-162.
[41]. Yusuf, M. (2023). Profesionalisme manajer proyek dan kualitas SDM dalam konstruksi. Jurnal Teknik Sipil dan Perencanaan, 25(1), 67-84.
[42]. Zulian, A. (2024). Pengaruh keahlian, kecerdasan emosi, kepemimpinan, dan negosiasi terhadap kinerja proyek. Jurnal Manajemen Bisnis, 17(1), 112-128.
[43]. Zulaecha, S. (2021). Peran project manager terhadap keberhasilan proyek konstruksi. Jurnal Rekayasa Konstruksi Mekanika Sipil, 4(2), 89-102.
Downloads
Published
How to Cite
Issue
Section
License
Copyright (c) 2026 ASTONJADRO

This work is licensed under a Creative Commons Attribution-ShareAlike 4.0 International License.
Paper submitted to ASTONJADRO is the sole property of the Astonjadro Journal. Unless the author withdraws the paper because he does not want to be published in this journal. The publication rights are in the journal Astonjadro.ASTONJADRO
LICENSE
This work is licensed under a Creative Commons Attribution-ShareAlike 4.0 International License.
Based on a work at http://ejournal.uika-bogor.ac.id/index.php/ASTONJADRO