Comparison of Wall Construction Costs Using Brick, Batako, and Hebel Materials in Denpasar City

Authors

  • Ni Kadek Astariani INDONESIA
  • I Gusti Ngurah Eka Partama INDONESIA
  • I Gusti Ngurah Gede Dirgayusa Putra INDONESIA
  • I Gusti Lanang Bagus Eratodi INDONESIA

DOI:

https://doi.org/10.32832/astonjadro.v15i2.22588

Keywords:

comparison, materials, brick, hebel, walls.

Abstract

A construction project is a series within a certain scope where work in the field certainly has a limited time. Several previous researchers conducted research on the comparative cost of wall materials and found that the cost of installing walls using bricks was cheaper than red bricks or bricks. Based on the results of previous research with a comparison of the costs of the three wall materials, namely brick, brick and Hebel as wall materials, in this research we will compare the work costs of the three materials Brick, Brick and Hebel with a case study in the SMA Negeri 9 Building Construction Project Denpasar. From the calculation of wall construction costs in the Denpasar 9 Public High School building construction project, the results obtained were that for walls made of brick material it was IDR. 425,894,615.49, walls made of brick material amounting to IDR 401,891,935.33 and for walls made of hebel material IDR. 507,619,946.90. From the results of the comparison of the total wall construction costs in the Denpasar 9 State High School Building Project, the cost of wall work using brick material is 5.80% higher compared to wall work using brick material, the cost of wall work using brick material is 17.65% lower than wall work using brick material. hebel material and the cost of wall work using brick material is 24.47% lower compared to wall work using hebel material. Brick material has the lowest work costs, brick material has higher work costs than brick but lower than hebel, while hebel material has the highest work costs.

Author Biographies

Ni Kadek Astariani, INDONESIA

Program Studi Teknik Sipil, Universitas Ngurah Rai, Denpasar, Bali

I Gusti Ngurah Eka Partama, INDONESIA

Program Studi Teknik Sipil, Universitas Ngurah Rai, Denpasar, Bali

I Gusti Ngurah Gede Dirgayusa Putra, INDONESIA

Program Studi Teknik Sipil, Universitas Ngurah Rai, Denpasar, Bali

I Gusti Lanang Bagus Eratodi, INDONESIA

Program Studi Teknik Sipil, Universitas Ngurah Rai, Denpasar, Bali

References

[1] Tjaturono. (2004). Penerapan Produktivitas Tenaga Kerja Aktual dan modifikasi Penjadwalan dengan Metode Fast Track untuk Mereduksi Biaya dan Waktu Pembangunan Perumahan. Makalah Seminar REI Jatim.

[2] Adiasa, A., Prakosa, D., Hatmoko, J., & Santoso, T. (2014). Evaluasi penggunaan beton precast di proyek konstruksi. Karya Teknik Sipil, Vol. 3, No. 4.

[3] Anam, C., & Sugiyanto. (2022). Analisa Efisiensi Penggunaan Bata Merah Dibanding Bata Ringan Pada Proyek Pembangunan Gedung Madrasah Tsanawiyah Salafiyah Kerek Tuban. Rang Teknik Journal, 236.

[4] Arya, I. M. (2020). Perbandingan Waktu dan Biaya Pada Pekerjaan Pasangan Dinding Dengan Metode Time Study Pada Proyek Konstruksi Gedung. Universitas Hindu Indonesia, 27-35.

[5] Harahap, S. (2021). Analisa Perbandingan Biaya Serta Waktu Pelaksanaan Material Dinding Batu Bata dan Batako Pada Rumah Type 36. Jurnal Education and development Institut Pendidikan Tapanuli Selatan, 21-23.

[6] Suseno, H. (2022). Analisa Perbandingan Biaya Dinding Bata Ringan dan Bata Merah Bantuan Rumah Tidak Layak Huni. Jurnal PENA Vol. 36 No. 2, 160-168.

[7] Dewanto, R. (2012). Perbedaan Antara Bata Merah dengan Bata Ringan.

[8] Djojowirono, S. (2005). Yogyakarta : KMTS. Manajemen Konstruksi (Edisi Empat).

[9] Manto, J. (2016). Jurnal Ilmiah “Mengidentifikasi Durasi dan Tenaga Kerja Berdasarkan Analisa Harga Satuan Pekerjaan (AHSP) Pada Perencanaan Pekerjaan Perumahan Villa Idaman Boalemo.

[10] Faisal, M. (2001). Analisis Penyebab Terjadinya Cost Overruns pada Proyek Konstruksi Bangunan Gedung. Universitas Islam Indonesia, 16-17.

[11] Fransiska, R. (2018). Analisa Perbandingan Biaya Material Pasangan Bata Merah, Bata. Fakultas Teknik Universitas, C7.1-C7.6.

[12] Widiastuti, D. U. (2016). Analisis Biaya Penggunaan Material Dinding. Fakultas Teknik Universitas Negeri.

[13] Kementrian PUPR . (2023). Surat Edaran nomor 73/SE/BK/2023. Jakarta Selatan: Bina Konstruksi.

[14] Monica, F. (2019, December 6). Project Control, Line Balancing, Kriteria Pengendalian dan Laporan Kemajuan Proyek. Retrieved from Wordpress: http://monica.blog.widyatama.ac.id/2019/12/06/project-control-line-balancing-kriteria-pengendalian-dan-laporan-kemajuan-proyek/

[15] Ngabdurrochman. (2009). Makalah Tugas Matakuliah Teknologi Beton, Universitas Sains Al Qur’an, Wonosobo. Teknologi Beton Ringan.

[16] Sugiyono. (2008). Memahami Penelitian Kualitatif. Bandung: Alvabeta.

Published

2026-05-29

How to Cite

Astariani, N. K., Partama, I. G. N. E., Putra, I. G. N. G. D., & Eratodi, I. G. L. B. (2026). Comparison of Wall Construction Costs Using Brick, Batako, and Hebel Materials in Denpasar City. ASTONJADRO, 15(2), 626–632. https://doi.org/10.32832/astonjadro.v15i2.22588

Issue

Section

Articles