Analisis Biaya dan Waktu Percepatan Proyek Pembangunan Rusun At-Tanwir Cianjur dengan Penambahan Jam Kerja Menggunakan Metode TCTO
DOI:
https://doi.org/10.32832/komposit.v9i2.17785Keywords:
Time Cost Trade Off, Microsoft Project , Analysis of Unit Prices , acceleration, crashingAbstract
The At-Tanwir Foundation’s Flats Construction Project at Cianjur Regency, West Java; aims to provide housing for students and promote education. Therefore, expediting the construction process for immediate utilization is essential to meet the housing needs. One alternative for expediting the project is to increase working hours using the time-cost trade-off method. The purpose of acceleration is to anticipate delays in the project and shorten the project implementation time. This study uses data such as Project RAB, Plan S Curve, a List of Unit Prices of Materials, Tools, and Labor, and an Analysis of Unit Prices of Work. Microsoft Project 2019 software assists in data processing to identify critical paths. After accelerating work on critical activities, the analysis showed that by adding 3 hours of overtime, the project duration can be reduced to 100 working days, which is 15% faster than the normal duration of 119 working days. The optimal cost for this duration is IDR 808,750,195.52, which is 0,69% lower than the normal cost of IDR 803,164,902.33, with a cost difference of IDR 5,585,293.19.
References
Abdillah, M. G., & Kurniawan, S. (2022). Analisis Metode Time Cost Trade Pada Pembangunan Perpustakaan IAIN Metro. Jurnal Jumatisi, 3(1). https://doi.org/10.24127/jumatisi.v3i1.3709
Arthono, A., Rahayu, D., & Purbakawaca, R. (2024). Analisis Biaya dan Waktu dengan Menggunakan Metode Nilai Hasil (Earned Value) pada Proyek Pembangunan Mako Polres Jakarta Barat. Jurnal Komposit: Jurnal Ilmu-Ilmu Teknik Sipil, 8(2), 309–315. https://doi.org/10.32832/komposit.v8i2.15427
Erfaliani, A. P., Pradika, J. D., Hendriyani, I., & Pratiwi, R. (2024). Analisis Waktu dan Biaya pada Proyek Pembangunan Pasar Induk Senaken Kabupaten Paser dengan Metode Time Cost Trade Off (TCTO). Jurnal Komposit: Jurnal Ilmu-Ilmu Teknik Sipil, 8(2), 297–308. https://doi.org/10.32832/komposit.v8i2.15938
Hermawan, I. P. Y., Sunatha, I. G. N., Wangsa, A. A. R. R., & Sadewa, K. A. (2023). Analisis Percepatan Waktu Pelaksanaan Proyek Dengan Penambahan Jam Kerja (Studi Kasus Pembangunan Lahan Parkir Rumah Sakit Bangil Medika Canti). Jurnal Unmasmataram, 17(2), 638–644. https://journal.unmasmataram.ac.id/index.php/GARA/article/view/467
Khabibulloh, M., & Adi, T. J. W. (2022) Optimasi Waktu Dan Biaya (Time Cost Trade Off-TCTO) Menggunakan Particel Swarm Optimization (PSO). Jurnal Teknik ITS, 11(3). DOI: 10.12962/j23373539.v11i3.96419
Keputusan Mentri Tenaga Kerja dan Transmigrasi Republik Indonesia Nomor Kep.102/Men/VI/2004 tentang Waktu Kerja Lembur dan Upah Kerja Lembur.
Malifa, Y., Dundu, A. K. T., & Malingkas, G. Y. (2019). Analisis Percepatan Waktu Dan Biaya Proyek Kontruksi Menggunakan Metode Crasing (Studi Kasus: Pembangunan Rusun IAIN Manado). Jurnal Sipil Statik, 7(Juni), 681–688. https://ejournal.unsrat.ac.id/v2/index.php/jss/article/view/23649
Mardiaman, M. (2022). Perencanaan dan Penjadwalan Kontruksi (M. Husein Maruapey, Ed.; 1st ed., Vol. 1). KBM Indonesia.
Mardiaman, M. (2024). Metodologi Penelitian (Mardiman, Ed.; 1st ed., Vol. 1). KBM Indonesia.
Nathasia, C. A., Budiman, J., & Norman. (2022). Analisis Percepatan Waktu dan Biaya Dengan Metode Time Cost Trade Off (TCTO). Jurnal Pendidikan Dan Aplikasi Industri, 9(1), 45–54. https://doi.org/10.33592/unistek.v9i1.2185
Nurafifah, N. M., Dewita, H., & Sembiring, K. (2025). Analisis Waktu pada Pekerjaan Tambahan Proyek Pembangunan Gedung PT. Petrokimia Gresik . Jurnal Komposit: Jurnal Ilmu-Ilmu Teknik Sipil, 9(1), 101–108. https://doi.org/10.32832/komposit.v9i1.16449
Prabowo, P. P., Apriliano, D. D., & Mulyono, T. (2023). Analisis Percepatan Waktu dan Biaya Konstruksi dengan Penambahan Jam Kerja (Lembur) Menggunakan Metode Time Cost Trade Off (Studi Kasus Proyek Pembangunan Rumah Tinggal di Jalan Salak Kota Tegal). Keteknikan Dan Informatika, 1(3), 122–132. https://ejournal.eraliterasi.com/index.php/erasain/article/view/85/71
Riza, M. N., & Witjaksana, B. (2022). Analisis Biaya dan Waktu dengan Menggunakan Metode least Cost Analysis Proyek Pembangunan Gedung Ruang Kelas Baru MAN Kota Surabaya. Jurnal Kacapuri, 5(1). https://ojs.uniska-bjm.ac.id/index.php /jurnalkacapuri/article/view/7560/4025
Silalahi, Y. I., Masthura, L., & Fahriana, N. (2023). Analisis Faktor - Faktor Penentu Keberhasilan Proyek Konstruksi Berdasarkan Mutu, Biaya dan Waktu. Jurnal Komposit: Jurnal Ilmu-Ilmu Teknik Sipil, 7(2), 233–240. https://doi.org/10.32832/komposit.v7i2.14240
Sulistyo, A. B., Kusdianto, A., & Wirawati, S. M. (2023). Analisis Manajemen Proyek dengan Sistem Umbrella Contract Menggunakan Metode Time Cost Trade Off (Studi Kasus: PT Jaya Inti Teklindo). Jurnal Penelitian Dan Aplikasi Sistem Dan Teknik Industri, XVII(1), 43–57. https://www.academia.edu/download/107118745/17528-58446-1
Sunathan, I. G. N., Praganingrum, T. I., & Nata, I. P. S. C. P. (2023). Analisis Percepatan Waktu Pelaksanaan Proyek Berbasis Microsoft Projek (Studi Kasus: Pembangunan Renovasi Hotel Laguna Resort and Spa Nusa Dua). Ganec Swara, 17(2), 594–601. https://doi.org/10.35327/gara.v17i2.461
Downloads
Published
How to Cite
Issue
Section
License
Copyright (c) 2025 Jurnal Komposit: Jurnal Ilmu-ilmu Teknik Sipil

This work is licensed under a Creative Commons Attribution-NonCommercial-ShareAlike 4.0 International License.
Authors who publish with this journal agree to the following terms (Penulis yang mengajukan publikasi artikel telah menyetujui hal berikut):
- Through this publication, the author agree to submit the copyright of article writing to Jurnal Komposit: Jurnal Ilmu-ilmu Teknik Sipil. This copyright submission takes the form of, but is not limited to: reproduction of the article and parts therein, including photographic reproductions; distribution of articles through printed and electronic documents; and translation of articles(Bahwa melalui publikasi ini, hak cipta penulisan artikel diserahkan kepada Jurnal Komposit: Jurnal Ilmu-ilmu Teknik Sipil. Penyerahan hak cipta ini berupa, namun tidak terbatas pada: perbanyakan artikel dan bagian di dalamnya, termasuk reproduksi fotografi; penyebarluasan artikel melalui dokumen cetak dan elektronik; serta penterjemahan artikel).
- The authors agree to the terms of the Copyright Notice, according to Creative Commons Attribution-NonCommercial-ShareAlike 4.0 International License., which will apply to this article if and when it is published by Jurnal Komposit: Jurnal Ilmu-ilmu Teknik Sipil. (Para penulis setuju dengan ketentuan Pemberitahuan Hak Cipta, sesuai dengan Lisensi Internasional Creative Commons Attribution-NonCommercial-ShareAlike 4.0., yang akan berlaku untuk artikel ini jika dan ketika diterbitkan oleh Jurnal Komposit: Jurnal Ilmu-ilmu Teknik Sipil).

This work is licensed under a Creative Commons Attribution-NonCommercial-ShareAlike 4.0 International License.

.png)